FG asks Lagos-Ibadan railway contractor to work day, night
Rasheed Bisiriyu
The Federal Government has advised the
contractor handling the 150-kilometre Lagos-Ibadan railway project,
China Civil Engineering Construction Corporation, to work day and night
to avoid extending its delivery date beyond December this year.
The Minister of Transportation, Mr.
Rotimi Amaechi, stated this on Monday after the monthly meeting of the
Project Steering Committee with the CCECC team at the Papalanto
rail/work station in Ogun State.
Although he acknowledged that there had
been remarkable progress in the pace of work done in the last one month,
he noted the rainy season would pose a major challenge.
“The rain will be a major setback on the
plans. The CCECC is the company that has to find the engineering
solution to this. But whether they find a solution or not, the element
cannot be ignored. That’s why I advised that they should work day and
night to achieve the set goals,” the minister stated.
Amaechi also said the contractor would
begin the laying of the track on the new line next month, and was
optimistic that the December delivery date for the $1.5bn standard gauge
rail line was feasible.
According to him, a train station in
Abeokuta, Ogun State, had to be moved to the North-West to avoid
demolishing about 1,004 buildings in the area.
Amaechi said the biggest challenge of
the project at the moment was with the Lagos corridor where many
utilities such as power lines, water pipelines and bridges were on the
rail’s right of way, thus hindering the construction.
He stated that some water pipelines belonging to the Lagos State Government would have to be relocated.
The minister said a committee headed by
the Chairman of the Nigerian Railway Corporation, Usman Abubakar, with
the Managing Director, NRC, Fidet Okhiria, and representatives of the
Nigerian National Petroleum Corporation and Nigerian Army had been
constituted to come up with “the best engineering solution that would
have minimal impact on the people.”
The new railway is the first phase of
the Lagos-Kano standard gauge line with an extension from Kaduna to
Abuja. The Kaduna-Abuja extension has been completed and running, while
the Lagos-Ibadan is expected to begin early next year, with the loan
request for the project already forwarded to the China Exim Bank for
approval.